PROUD   TO   SERVE   THE   NATION........                                                                                                                      LETS   GROW   AS   PROSPEROUS   NATION.......                                                                                                                     ANOTHER   STEP   OF   FAUJI   FOUNDATION   TOWORD   BETTER   EMPLOYMENT   OPPORTUNITIES   FOR   OUR   SINDHI   BROTHERS.....

   ||HISTORY

  • The Project was conceived during 2003 and registered in April 2004.
  • Feasibility Study of the project carried out by Fichtner, Germany and submitted to PPIB on 24 June 2005. 
  • The company was incorporated on 10 November 2005 with title of Foundation Power Company Daharki Limited under Companies’ Ordinance, 1984.
  • Pre-Notice to Proceed (PNTP) was issued to Doosan Heavy Industries & Construction Company Ltd on 19 November 2006.
  • Engineering Procurement & Construction Contract (EPC) was awarded to Doosan Heavy Industries & Construction Company Ltd, Korea on 2 February 2007.
  • National Electric Power and Regulatory Authority (NEPRA) awarded Power Generation License on 22 February 2007.
  • Sindh Environmental Protection Authority (SEPA) issued NOC on 10 February 2007.
  • The Stone Laying Ceremony was performed by The President of Islamic Republic of Pakistan, General Pervez Musharaf (Retd) on 24 May 2007.
  • Gas Supply Agreement (GSA) was signed with Mari Gas Company Ltd (MGCL) on 27 August 2007.
  • Gas Transmission License obtained from OGRA on 27 August 2007.
  • Power Purchase Agreement (PPA) was signed between FPCDL and Water & Power Development Authority (WAPDA) on 29 August 2007.
  • Contract for Construction of Gas Pipe Line awarded to Marathon Construction Company Limited on 23 November 2007.
  • Contract for Design Review of Civil Works awarded to National Engineering Services Pakistan (Pvt) Ltd on 10 December 2007.
  • Civil Contracts were awarded to Dawn Enterprises in March 2008 and Arcika Traders & Contractors in July 2008.
  • Operational & Maintenance Contract was signed with Korea Plant Services & Engineering Company, Korea on 04 August 2008.
  • First Firing of Gas Turbine achieved on 29 October 2009.
  • Combined Cycle Mode of the Power Plant commenced from 30 December 2009.
  • Full Load Operation (185 MW) of the Plant achieved on 03 January 2010.
  • The Plant achieved COD on 16 May 2011.